Science casework has been delivered, above ceiling inspections are ongoing, lobby roof is completed, tennis courts are completed, regular casework is arriving this week, chiller will start up next week, ceramic tile in kitchen areas will start first week of July, VCT will start first week of July, bathroom floor tile is ongoing, servery tile has been delivered to site, kitchen equipment is at the warehouse until the tile is complete, steel for the gym will arrive at the end of the month, first FFE delivery will be on July 14, locker installation will commence July 15, trees at main entrance are being cleared, elevator installation is in progress.